01/17/2022
Ray
Green Valley, AZ
Ally Attwood came to our home in Green Valley on October 6th after setting an appointment with us at the Home Show. We had solar on another home previously, so we asked questions and came to an agreement on installing solar at this home. We received updates during the design and permitting process and that took about 1 month. Then, Saguaro Solar scheduled us with an installation date of November 30th. The installation took only until about 1 p.m. and the crew left our roof and surrounding ground in great shape. Saguaro Solar passed inspection with the county a week later with every checked out and then December 16th was the time when TEP sent the notification giving Saguaro Solar the approval to flip the switch and for us to be fully connected to operate. The cost was close to our expectation and the communication from Saguaro Solar and Ally Attwood was much better than we had anticipated.
System size (kW): 6.4
System price: $14,858
Price include the Federal Tax Credit or incentives: No