Office location: 1181 Cadillac Court, Milpitas CA, 95035
01/21/2025
Richh
Hercules, CA
The 28 panel/two Tesla battery system was installed in two days with minor delay caused by a temporary shortage of parts. Final inspection had been delayed by a minor change to the relocation of an emergency shut-off switch. Still awaiting final inspection by the City and connection to the grid. All Sunrun staff have been a pleasure to work with during the process that started in early November with plan design; installation in mid-November. Now at mid-Januarys awaiting final city inspection.
System size (kW): 11.34
System price: $314
Year installed: 2024
Price include the Federal Tax Credit or incentives: Yes
Sunrun Inc. reply
01/22/2025
Thank you so much for being part of our Sunrun family, Richh!