Process started middle of 2024. Initially expected for project to finish by August. By December, finally got approval from utility and county planning and building department. Panels were installed on December 23, 2024 and still waiting for the project to be finished. Been told project needed a "PV stamp" but utility and county know nothing about this. Still paying utility and now have to start paying for the system. Starting to get depressed.
System size (kW): 23
System price: $82,000
Year installed: 2025
Price include the Federal Tax Credit or incentives: Yes
Energy Service Partners (ESP) reply
03/17/2025
Brian, we're very sorry to hear about the delays. We're unable to confirm a project in our system based on your screen name and zip/location of the project as listed here, but we will be happy to assist if you reach out to our support teams.